| You can discover the progress of work. 2003 - Spring - Summer 2003: the cottage plans, specifications, building permits deposition, various issues.
- Fall 2003: cutting trees (fir, Douglas fir, oak ...) povenant local forest (my father) to 30 km of the future cottage, prepared according to the size ...
- December 2003 / January 2004: sawing wood for the frame, drying ...
2004
 - January / February 2004: the demolition of very old floors, the fireplace, bread oven (to be reassembled later worry !!!).
- March 2004: start of masonry moving inside, sewage, septic tanks, pit Canadian slab of the garage, expansion of the garage door, creation of the slab on the ground floor, windows, Bay glass, creating doors, installation of electrical conduit, installation of two tanks to collect rainwater.
- July 2004: sawing wood for the floors.
- September-October 2004: elevation of the walls and expansion, linking interior lintels.
- Late October - early 2004 novemvre: treatment of the structure, installation of the structure and coverage of the house, razing of the roof, chimney and bushel basketful, roughing the floor, painting some of the boards of the roof of the terrace covered (before installation).
- December 2004: installation of windows, the front door and back door.
2005 - February 2005: insulation of all exterior walls with glass wool, treatment and painting of the boards of floors (two coats before laying).
- March 2005: zinguerie roof (Aberg fireplace, hallways).
- Late April-May: installation of doors and interior partitions Carrobric early, laying of electrical conduit.
- May 2005: installation of beams, joists, stairs wood, paint the floor joists and stairs (two layers), receipt of wooden walls and floors, preparation: planing, tongue and groove ...
- June 2005: installation of double-door interior trimming of the basement, sanding and cut stone joints and brushed the inside wall and facades, basketful of chimney, forming metalling terrace.
- July 2005: laying of heating pipes in the slab, tiling on the ground floor and bathrooms, connection to water supply, electricity and partitions on the 1st floor.
- August 2005: partitions and electricity first floor.
- September 2005: partitions and electricity first floor, treatment and painting boards walls (two coats before laying). .
- October 2005: selection of appliances, furniture, walls and electricity.
- Late November-December 2005: water and heating, electricity and partitions.
- December 2005: Installation of the flooring, sanding, stain and vitrification, vitrification of the stairs, installation of electricity and end walls, wallpapering and painting of walls, installation of kitchen furniture, appliances, chandeliers, manufacture of certain beds, room layout (furniture, bedding, deco ...) ...
2006 - January 2006: tiling the kitchen wall, fabrication, and installation of shade doors of the kitchen furniture, finish carpentry (installing corner beads, card, complaints), raises blinds.
- February 2006: opening of shelter.
2007 - March 2007: the work of the wall (stone joints) Speaker of the land.
- May 2007: Planning for outdoor: grass, flowers ...
2008 - March-April: painting the garage floor and tiling the stairs between the basement and ground floor.
- Autumn: development of external: provision of stone trough and an old boiler potatoes to plant flowers on the patio, small plantation of fruit trees (black currants, gooseberries) ...
2010 - March: manufacture of wooden benches for the outside with the recovery of old beams of the house.
|